Construction to start towards the end of the week of July 20th or the first part of the week on July 27th. Weather may impact this start date. Construction will start at the west end of the project area around the Northwestern Dr. and HWY 7 intersection. While work is underway the road will be closed to thru traffic.
Local traffic will have access to their properties a majority of the time; however, there will be some times (should be limited to eight hours or less) where access will be prohibited during construction. In these events the contractor and/or City staff will provide property owners advance notice so that other arrangements can be made. The contractor will ensure emergency access to the area at all times.
Temporary Access |
No comments:
Post a Comment